Test Your Knowledge - Free MCQ PRACTICE
SOFTWAREENGINEERING
by Dr K Chaudhry
MACHINIST
ELECTRICIAN
PHYSIOLOGY
OPERATIVEDENTISTRY
COMPUTER
PEDODONTICS
OBSGYN
COMMUNITYMEDICINE
PSYCHIATRY
BIOCHEMISTRY
SOFTWAREENGINEERING
ENT
PERIODONTICS
RADIOLOGY
ANAESTHESIA
PAEDIATRICS
PHYSICS
GENERALKNOWLEDGE
DERMATOLOGY
PATHOLOGY
ORTHOPAEDICS
MEDICINE
DRIVINGTEST
CHEMISTRY
BIOLOGY
ANATOMY
PHARMACOLOGY
BIOTECHNOLOGY
MICROBIOLOGY
OPHTHALMOLOGY
ELECTRONICENGINEERING
INSURANCE
FORENSICMEDICINE
FITTER
ENDODONTICS
DENTISTRY
SURGERY
A fresh set of 20 random questions is generated every time you open this page and every time you refresh it.
For each of the following multiple choice questions, choose the most appropriate answer :

1. An ordering system may be adapted to cope with a centralized ordering process in one company and a distributed process in another.” Which category the example belong to?
A. a) Process specialization
B. b) Platform specialization
C. c) Environment specialization
D. d) Functional specialization

2. Who proposed the spiral model?
A. Barry Boehm
B. Pressman
C. Royce
D. IBM

3. The CMMI assessment is based on a x-point scale. What is the value of x?
A. a) 0
B. b) 2
C. c) 4
D. d) 6

4. What is the purpose of a Status Report in project management?
A. a) To disregard timelines
B. b) To avoid project deliverables
C. c) To limit team interactions
D. d) To update stakeholders on project progress and milestones

5. How many stages are there in process improvement?
A. a) three
B. b) four
C. c) five
D. d) six

6. Which of the following is not an effective project manager trait?
A. a) Problem solving
B. b) Managerial identity
C. c) Influence and team building
D. d) None of these

7. Link based measures rely on ___________ structure of a web graph to obtain related pages.
A. a) Embedded
B. b) Hyperlink
C. c) Dynamic
D. d) All these

8. Which of the following is not a build system feature?
A. a) Minimal recompilation
B. b) Documentation generation
C. c) Storage management
D. d) Reporting

9. Which of the following is not a direct measure of SE process?
A. a) Efficiency
B. b) Cost
C. c) Effort Applied
D. d) All these

10. Define Agile scrum methodology.
A. project management that emphasizes incremental progress
B. project management that emphasizes decremental progress
C. project management that emphasizes neutral rogress
D. project management that emphasizes no progress

11. Which one is not a size measure for software product?
A. a) LOC
B. b) Halstead’s program length
C. c) Function Count
D. d) Cyclomatic Complexity

12. Which of the following is not a project factor that should be considered when planning the structure of software developing teams?
A. The rigidity of the delivery date
B. The degree of sociability required for the project
C. High frustration caused by personal, business, or technological factors that causes friction among team members
D. The difficulty of the problem to be solved

13. Which test refers to the retesting of a unit, integration and system after modification, in order to ascertain that the change has not introduced new faults?
A. a) Regression Test
B. b) Smoke Test
C. c) Alpha Test
D. d) Beta Test

14. The incorrect activity among the following for the configuration management of a software system is ________
A. Version management
B. System management
C. Change management
D. Internship management

15. A software might allow a user to interact via
A. a) keyboard commands
B. b) mouse movement
C. c) voice recognition commands
D. d) All these

16. Software is defined as ___________
A. set of programs, documentation & configuration of data
B. set of programs
C. documentation and configuration of data
D. None of the mentioned

17. Which frameworks support the development of system infrastructures such as communications, user interfaces, and compilers?
A. a) Middleware integration frameworks
B. b) System infrastructure framework
C. c) Enterprise application frameworks
D. d) Web application frameworks

18. Usability can be measured in terms of:
A. a) Intellectual skill to learn the system
B. b) Time required to become moderately efficient in system usage
C. c) Net increase in productivity
D. d) All these

19. The Incremental Model is combination of elements of
A. a) Build & FIX Model & Waterfall Model
B. b) Linear Model & RAD Model
C. c) Linear Model & Prototyping Model
D. d) Waterfall Model & RAD Model

20. Cost and schedule are a part of
A. a) Product Metrics
B. b) Process Metrics
C. c) Project Metrics
D. d) All these